M27 River Hamble Bridge – Strengthening & Bridge Upgrading 2008

EKSPAN were successful in securing the design and manufacture of 60 new stainless steel mechanical bearings. EKSPAN were also responsible for the temporary works design and bridge jacking. The works was successfully completed in September 2008.
Hydro-Electric High Head Pipeline Saddle Refurbishment

The hydro-electric power station is located near the river Conwy in North Wales. The high head pipeline, originally constructed around the 1930’s, delivers water to the power station from the reservoir to power the turbines.
Low Head stool and bearing replacement Dolgarrog Power Station

EKSPAN were instructed to replace bearing stools assemblies on the low head high pressure pipeline for plinths 2, 4 and 6.
Astana Stadium

EKSPAN’s Solution
The roof construction of the stadium created a number of technical issues with respect to managing dynamic loads. Additional rotations and movements had to be considered at the main support positions to accommodate the nature of the mobile roof structure.
Adu Dhabi Airport – Midfield Terminal Bearing Supply & Inspection Of Installation

EKSPAN were instructed by Eversendai Engineering to design, manufacture and supply 522 no mechanical and elastomeric bearings for installation on 58 bridges, on two levels.
M1 Tinsley Viaduct Strengthening & Upgrading

EKSPAN were instructed by Eversendai Engineering to design, manufacture and supply 522 no mechanical and elastomeric bearings for installation on 58 bridges, on two levels.