A38 Gloucester
Road Flyover.

24 replacement bearings.
Designed, manufactured and installed by EKSPAN.

Explore the project

LOCATION

Bristol

REPLACEMENT BEARINGS

18 rocker · 6 spherical

COMPLETED

December 2025

EKSPAN’S ROLE

Design, manufacture & installation

EXISTING STRUCTURE. SPECIALIST INTERVENTION.

Replacing bearings.
Managing the
support beneath.

EKSPAN designed, manufactured and installed 24 replacement bearings at the A38 Gloucester Road Flyover in Bristol.

The replacement comprised nine rocker bearings at each abutment and three spherical bearings at each of the north and south pier locations. Temporary support, hydraulic jacking and associated concrete repairs connected the bearing work with the existing structure.

Completed in December 2025, EKSPAN’s bearing replacement package formed part of the wider refurbishment scheme.

Explore our manufacturing  

TEMPORARY WORKS. PERMANENT SUPPORT.

Support through
every stage.

Installing the pier props was a key challenge.
Access, support and bearing replacement brought together.

Telehandler positioning a steel beam beneath the A38 flyover at night

01

Temporary propping at the piers

Installing the temporary props at the pier locations was a key challenge identified by the project team. The arrangements were positioned around the existing concrete piers beneath the flyover deck.

Replacement bearing above exposed reinforcement during concrete repairs

02

Concrete repairs & preparation

The documented repair approach included local concrete breakout, preparation of exposed reinforcement, concrete reinstatement and bearing grouting. These interfaces connected the replacement bearings with the existing structure.

DESIGNED. MANUFACTURED. INSTALLED.

24 bearings.
One coordinated
replacement package.

EKSPAN’s replacement package covered 18 rocker bearings at the abutments and six spherical bearings at the piers. Existing upper tapped holes were reused to connect the new bearings.

01

18 rocker bearings

North abutment: 9 rocker bearings.
South abutment: 9 rocker bearings.

02

6 spherical bearings

North piers: 3 spherical bearings.
South piers: 3 spherical bearings.

03

Connecting to the existing structure

Existing upper tapped holes reused to connect the replacement bearings.

Explore bridge bearings  

ENGINEERING KNOWLEDGE. PRACTICAL DELIVERY.

From bearing design
to site installation.

18 rocker bearings. 6 spherical bearings.
Temporary propping, hydraulic jacking and controlled load transfer.
Completed in December 2025.

A CLOSER LOOK

Real project photography.
Select an image to explore the detail.

Photographs show different locations and stages of the works, rather than a continuous construction sequence.

MORE ENGINEERING IN PRACTICE

A different structure.
The same practical approach.

Explore Govan–Partick Bridge  

LET’S START WITH YOUR PROJECT

Planning a bearing
replacement project?

Bearing replacement, temporary works and associated structural repairs.
Talk it through with the EKSPAN team.