With more complex and substantial machining demands for projects, Ekspan now operate a state-of-the-art Hurco DCX3226i CNC machine, an essential addition to their in-house manufacturing facilities.
USL Ekspan is the UK's largest quality bearing supplier and installer to meet demands both in the UK and worldwide.
USL Ekspan install an extensive range of mechanical and elastomeric expansion joints and seal joints to CD358 standards.
Bridge jacking and temporary works are an essential part of most bearing replacement and refurbishment operations, ensuring works are carried out safely and efficiently without affecting the integrity of the structure.
The importance of carrying out bearing and expansion joint inspections by proficient and competent engineers who understand their functionality can often be key to maximising a structure’s lifespan and avoiding major, unexpected, emergency repair costs.
USL Ekspan have carried out a number of projects for swing bridges and foot bridges. From design, fabrication of all structural components, to trial erection and final installation. Details of these type of bridge installations can be supplied on request.
Background
The Northern Hub, operated by Northern Hub Alliance and Network Rail, is a programme of planned work schemes to improve the existing rail infrastructure and upgrade the railway in the north of England. The works will provide improved rail travel/services and connectivity which will stimulate economic growth.
Skanska BAM Nuttall JV, one of the alliance partners, have been awarded the contract to deliver the Ordsall Chord - installation of a new rail link to provide a direct connection between Manchester Piccadilly, Manchester Oxford Road and Manchester Victoria stations. All major construction and maintenance works on the DSE146 Span 19 structure had to be completed within the 11 day Easter blockade as part of the construction for Ordsall Chord.
USL Ekspan’s Workscope
USL Ekspan was contracted by Skanska BAM Nuttall JV to install 2 no. T-Mat 80 expansion joints with concurrent installation of mechanical and elastomeric bearings on the DSE146 Span 19 structure. Ekspan installed 2 mechanical and 11 elastomeric bearings on the west abutment, and 1 mechanical and 12 elastomeric bearings on the east abutment.
T-Mat 80 expansion joint installed
This project involved 2 teams of USL Ekspan operatives working alternate shifts to provide 24 hours continuous working throughout the Easter bank holiday weekend rail possession.
The bearings were all set, temporary jacking assemblies were located to take the load of the structure from the SPMTS once driven into position. The joints were then installed during the weekend possession. The temporary jacking assemblies allowed the bearings to be fully installed during the week following the possession. Finally, the structural load was transferred off the temporary jacks and onto the permanent bearings.
Mechanical bearing installed
Elastomeric bearings installed
Difficult weather conditions, namely Storm Katie, unexpected site issues that arose requiring a quick resolve, and working to fit with other suppliers’ programmes made these series of works even more intense and challenging.
USL Ekspan’s successful delivery of this project is attributed to meticulous planning and efficient communication and collaboration within its own team, and with the external contractors also present carrying out major construction/improvements on the DSE146 Span 19 structure.