With more complex and substantial machining demands for projects, Ekspan now operate a state-of-the-art Hurco DCX3226i CNC machine, an essential addition to their in-house manufacturing facilities.
USL Ekspan is the UK's largest quality bearing supplier and installer to meet demands both in the UK and worldwide.
USL Ekspan install an extensive range of mechanical and elastomeric expansion joints and seal joints to CD358 standards.
Bridge jacking and temporary works are an essential part of most bearing replacement and refurbishment operations, ensuring works are carried out safely and efficiently without affecting the integrity of the structure.
The importance of carrying out bearing and expansion joint inspections by proficient and competent engineers who understand their functionality can often be key to maximising a structure’s lifespan and avoiding major, unexpected, emergency repair costs.
USL Ekspan have carried out a number of projects for swing bridges and foot bridges. From design, fabrication of all structural components, to trial erection and final installation. Details of these type of bridge installations can be supplied on request.
Background
The Mancunian Way, approximately 2 miles long, was designed and constructed in two stages during the 1960’s to ease city centre congestion.
This enabled traffic to be carried between the industrial areas of the east side through to Manchester Docks and Trafford Park in the west. The first stage was the construction of the dual carriageway east of the A6, and the second was the construction of a motorway with an elevated section between the A6 and A56.
The Flyover was built the same time Mancunian Way was extended east in 1992, and over time vehicular impact on this heavily used structure has caused considerable wear on the bearings which consequently have required periodic scheduled maintenance/replacement. Manchester City Council employed USL Ekspan to carry out works, overdue at the time, on the remaining 2 bearings located on the underside in the abutment chamber.
Existing bearing showing delamination and corrosion before removal
USL Ekspan’s Workscope
USL Ekspan were instructed to remove the 2 damaged bearings identified and replace these with 2 new guide bearings.
New guide bearing installed
Pre-works operations involved establishment and setup of a fully enclosed site compound with fencing panels to enable vehicle access within the working area; delivery and positioning of welfare unit; delivery and offloading of equipment and materials; scaffold installation to enable bearing access; preparation of specialist jacking system and hydraulic equipment to enable bridge jacking/de-jacking; and the setup of hydro-demolition equipment for bearing removal.
As jacking points were not present on the bridge additional specialist jacking had to be implemented using a propping system with temporary bearings. Without these removal and installation of the bearings would not have been possible.
All work procedures were completed safely and on time within the restraints of the project’s restricted access and working in a confined space.